PRACTICE ANSWER SHEET - FICTIONAL TRAINING ONLY

Baseline revision A
B12: 4 x 20 ft x 35 lb/ft = 2,800 lb.
B13: 2 x 12 ft x 26 lb/ft = 624 lb.
M21: 2 x 8 ft x 11.5 lb/ft = 184 lb.
Total: 8 pieces, 120 ft, 3,608 lb (1636.56 kg).

Revision B S101 schedule candidate
B12: 4 x 21 ft x 35 lb/ft = 2,940 lb. Other rows remain unchanged.
Total: 8 pieces, 124 ft, 3,748 lb (1700.06 kg).
Change: +4 ft and +140 lb (63.50 kg); the piece count is unchanged.

The issue to catch
S101-B changes the B12 schedule to 21 ft, but S201-B D1 retains 20 ft. A revision label or a marked change is not proof that every related value was coordinated. Do not silently pick one length. RFI-001 identifies both sheet/revision/detail references and asks for coordinated clarification. Keep B12 on hold. The revised schedule total is a comparison candidate, not a release total.

Expected project import
One new project copy; four saved records (two takeoffs, one drawing register, one RFI log); one unresolved follow-up item; zero of 18 checklist items marked. Four register entries: S101-A and S201-A superseded, S101-B and S201-B in review. The RFI remains open with no invented response. Existing project IDs and saved data are preserved.

Handoff exercise
Select one takeoff to avoid presenting the baseline and candidate as additive quantities. Include the register and RFI. Record the unresolved B12 hold. A printout documents an exercise and never authorizes fabrication.